| Tabuk Cement Company is industriously carrying over its aspired plan to complete its new core development projects. TCC continues to proceed with the remaining projects of this current phase as indicated below: |
Installation of a new filter before Plant's main stack |
|
|
In accordance with the environment protection policy, and out of the company's keenness to cope with all environmental standards in order to keep stack emitted dust ratio below the international rate of 50mg/Nm3, a contract has been signed with UBE - Janan, on 19/03/2004g, to supply and isntall a new dust filter which will achieve a 20mg/Nm3 emission ratio. Project kick off date was 17 May, 2004. The project was successfully commissioned by UBE, Japan on May, 2005. |
|
|